Houses in Markovo – construction progress as of 10 April 2025

Spring is in full swing (ha-ha-ha), and so is construction of the houses in Markovo. Here is what is happening on site as of today:

House 1:
The ground-floor walls are fully built, and the slab above them has been poured and is now curing. Work is under way on the first-floor columns, and the building is visibly growing every day.

House 2:
No new work has been carried out so far.

House 3:
Both floors are now built, and the first-floor slab has been poured and is also curing. The site is being prepared for building the roof. At the same time, the procedures for issuing Act 14 have been started.

House 4:
The external insulation has been fully applied. The window frames and windows have been fitted, along with additional insulation around the openings. The decorative bond elements around the windows are finished. Next come the facade render and fitting the HPL cladding on the eaves.

Current construction progress as of 10 April 2025

Follow us on social media for timely updates on the construction progress:
House Type 1 - House One
40%
House Type 1 - House Two
60%
House Type 1 - House Three
55%
House Type 2 - House One
85%

Contact us

We will be happy to give you more information about the project and answer any questions you have.

Office: 2 Lebed St, Plovdiv

Open in Google Maps
Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.