Houses in Markovo – construction progress as of 11 March 2025

As of 12 March 2025, construction of the houses in Markovo continues at a good pace. Here is the latest on each of them:

House 1: The foundations and ground-floor columns are complete. Masonry on the walls has begun, and formwork for the first slab will follow soon.

House 2: The roof is complete and waterproofing is under way in preparation for the facade insulation and render.

House 3: Today, 12 March, the first slab was poured. A curing period of at least three weeks follows.

House 4: Waterproofing is complete and facade insulation is now being fitted. Next week we will start the render, install the Italbond and HPL decorative elements and fit the window frames.

Current construction progress as of 12 March 2025

Follow us on social media for timely updates on the construction progress:
House Type 1 - House One
30%
House Type 1 - House Two
60%
House Type 1 - House Three
40%
House Type 2 - House One
75%

Contact us

We will be happy to give you more information about the project and answer any questions you have.

Office: 2 Lebed St, Plovdiv

Open in Google Maps
Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.