Construction of the houses in Markovo – phase one, four houses
The House Project Ltd project in Markovo village, Plovdiv, includes the construction of 16 detached family houses, each with a double garage and private yard. The houses offer modern architecture, a functional layout and quick access to the city of Plovdiv.
House in Markovo: progress of phase one - four houses
Phase one of the project includes four houses, and construction is progressing to plan:
-
House 1: Excavation for the foundations is complete, and concrete pouring is planned for this week. The same applies to House 3. Construction of the roof of House Type Two is now starting, and we expect "Act 14" to be issued very soon.
-
House 2: We are preparing to pour the first-floor slab, after which construction of the roof will begin.
These luxury houses in Markovo are designed with attention to detail and offer comfort and cosiness to their future owners. Located at the foot of the Rhodopes with a view over Plovdiv, they combine the peace of nature with the convenience of the city.
Main features of the houses:
-
Three bedrooms and two bathrooms with WC, plus a guest WC on the ground floor
-
Spacious living room with kitchen and dining area.
-
Double garage with direct internal access to the house and a utility room.
-
Private yard of between 348 m² and 404 m².
The project offers flexible payment plans tailored to clients' needs, as well as help with bank financing once Act 14 has been issued. High-quality materials and modern architecture ensure the durability and good looks of every house.