Houses in Markovo – construction progress as of 10 April 2025
Spring is in full swing (ha-ha-ha), and so is construction of the houses in Markovo. Here is what is happening on site as of today:
House 1:
The ground-floor walls are fully built, and the slab above them has been poured and is now curing. Work is under way on the first-floor columns, and the building is visibly growing every day.
House 2:
No new work has been carried out so far.
House 3:
Both floors are now built, and the first-floor slab has been poured and is also curing. The site is being prepared for building the roof. At the same time, the procedures for issuing Act 14 have been started.
House 4:
The external insulation has been fully applied. The window frames and windows have been fitted, along with additional insulation around the openings. The decorative bond elements around the windows are finished. Next come the facade render and fitting the HPL cladding on the eaves.