We continue building dream homes in Markovo
We are delighted to update you on the progress of another of our houses in Markovo. Work is going to plan, and our team continues to make every effort to ensure the high quality and durability of the project.
What has been achieved so far?
-
Excavation and foundations
The excavation was carried out precisely, then the blinding concrete was laid and the footings and foundations of the house were built solidly, following all building standards. -
Ground-floor walls built
Once the foundations were complete, our team built the ground-floor walls, which form the strong, stable base of the building. -
Slab above the ground floor
After the walls were completed, the slab above the ground floor was poured, providing a solid base for the first floor. -
Building the first floor
The first-floor walls are now built, and the structure is taking ever clearer shape. -
Formwork and reinforcement for the second slab
The formwork and reinforcement for the second slab are now fully prepared, bringing us closer to completing the load-bearing structure of the house.
What comes next?
Very soon we will pour the second slab and complete the building's load-bearing structure. After that we will move on to the next stages, including the roof structure and finishing works.
Why choose a house in Markovo?
Markovo combines the peace of nature with the convenience of being close to the city. This project is part of our mission to create functional, beautiful homes for our clients.